Contracts and Professional Liability

A contract decides who pays when costs run over, and negligence decides who pays when something fails.

A contractor starts a sewer job for a city, expecting it to cost $1,000,000 to build, and hits rock nobody knew was there. Nobody was careless. The job will now cost $1,300,000, because that's what the ground costs. So who finds the extra $300,000?

You can't work that out from the rock. It was settled months ago, when someone chose a type of contract. Under one type, the contractor earns more because of the rock.

The exam asks about contracts and liability, but the Handbook's Ethics and Professional Practice section is all licensure and conduct. It prints nothing on contract types, contract law, or civil liability, so everything here is yours to carry in.

Who pays when it runs over

Two parties to start. The owner wants something built and pays for it, here the city. The contractor builds it. Before the first shovel, neither knows what the job will really cost, so the contract has to settle one question in advance: who pays if it costs more than expected?

Every contract type answers it the same way. Look at what the contract fixes. What's fixed, the contractor has to live with. What's left open, the owner pays for.

Take the two extremes on the sewer job. Say the contractor expects to spend $1,000,000 and wants $100,000 of profit.

A lump sum contract, also called single fixed price, fixes the total. The contractor says $1,100,000, and the city pays $1,100,000 however the digging goes. With the rock, the contractor spends $1,300,000 and loses $200,000. Had the digging gone easily, the contractor would have kept the savings. Either way, the city's bill doesn't move. Real contracts often add a clause that hands surprise ground back to the owner, but left alone, a lump sum leaves it with the contractor.

Cost plus a fee fixes almost nothing. The city pays the actual cost plus a fee, say a fixed fee of $100,000. With the rock, the city pays $1,400,000, and the contractor still makes its $100,000.

0.8 0.9 1.0 1.1 1.2 1.3 1.4 Actual cost to build ($ million) Owner pays ($ million) 0.8 1.0 1.2 1.4 1.6 With the rock Lump sum Cost plus a fixed fee Estimate 1.1 1.4
What the owner pays as the actual cost moves

At the estimate, the two deals cost the city the same. They part ways only when reality does.

Fixing the rate, not the total

Some work sits in between. You know exactly what a cubic yard of excavation is. You just don't know how many you'll move until you're in the ground. A unit price contract fixes the rate per unit, and the owner pays that rate on whatever quantity is actually measured. So the risk splits in two: the quantity is the owner's, and what each unit costs to produce is the contractor's.

Worked Example Regrading a county road
1 of 3

A county needs a road regraded. Its engineer estimates 20,000 yd³ of excavation, but nobody will know the real quantity until crews are digging. Which contract type fits? And if the winning bid is $15/yd³ and crews end up moving 26,000 yd³, what does the county pay?

When nobody can describe the job

Lump sum and unit price have something in common: the contractor has to price something up front, a total or a rate. But nobody can price what nobody can describe. Ask for a lump sum on work that can't yet be defined, and you get a padded number, then a fight over every change.

A fast-tracked project runs into the same wall. To save calendar time, construction starts before the design is finished.

Checkpoint
1 of 2

A county wants to rehabilitate a 1920s pump station. Nobody will know how much of the old structure can be saved until crews open it up. Which contract type suits this work best?

A.
Lump sum
B.
Cost plus a fee
C.
Single fixed price
D.
Unit price

The deal that pays for spending

Now the deal from the Hook. Under cost plus a percentage of cost, the fee is a share of whatever gets spent, say 10%. At the estimate, that's $1,000,000 plus $100,000, the same as before. With the rock, it's $1,300,000 plus $130,000. The job went worse, and the contractor made $30,000 more.

You don't need a crooked contractor for this to matter. Picture the ordinary daily choices: the pricier pump or the cheaper one, one more crew on overtime or not. Under this deal, every dollar spent comes back as a dollar and ten cents, and every dollar saved costs the contractor a dime.

0.8 0.9 1.0 1.1 1.2 1.3 1.4 Actual cost to build ($ million) Contractor's fee ($ thousand) 0 50 100 150 200 With the rock Fixed fee Cost plus 10% Estimate 100 130
The contractor's fee as the actual cost moves

Two alternatives take that reward away. A fixed fee flattens the line: extra spending earns nothing, though the owner still pays the overrun. A guaranteed maximum price (GMP) goes further. It's cost plus a fee with a ceiling. The owner pays the actual cost and the fee up to an agreed maximum, and above that, the contractor pays. Set the ceiling at $1,200,000, and with the rock, the city's bill stops there. Next to the fixed-fee deal, that moves $200,000 onto the contractor: the last $100,000 of cost, and its $100,000 fee.

0.8 0.9 1.0 1.1 1.2 1.3 1.4 Actual cost to build ($ million) Owner pays ($ million) 0.8 1.0 1.2 1.4 1.6 With the rock Guaranteedmaximum price Cost plus a fixed fee Ceiling: 1.2 Contractorabsorbs this 1.2 1.4
A guaranteed maximum price puts a ceiling on the owner's bill
Checkpoint
1 of 2

A contractor on a cost plus 8% job can install a $200,000 standby generator or a $260,000 one, and both meet the specification. Why does this contract weaken the pressure to pick the cheaper one?

A.
The contractor's fee stays the same, so it can't gain by buying either one
B.
The contract caps the total, so any savings would go to the owner
C.
The contractor's fee rises with its spending, so the costlier one earns it $4,800 more
D.
The contractor pays for the generator out of its fee, so the choice is left to the owner

Lining them up

That's five deals and one rule: what's fixed, the contractor lives with, and what's left open, the owner pays for. Try it on both ends.

Checkpoint
1 of 2

Under which contract type does the contractor carry the most cost risk?

A.
Lump sum
B.
Unit price
C.
Guaranteed maximum price
D.
Cost plus a fixed fee

Here's the whole range. The ends follow straight from that rule, and they're what the exam asks about. The two bracketed deals split the risk differently, a GMP at its ceiling and unit price between rate and quantity, so don't read much into their order.

Contractor carries more of the cost risk Lump sum Fixes the total price Guaranteed maximum price Fixes a ceiling on the total Unit price Fixes the rate per unit Cost plus a fixed fee Fixes only the fee Cost plus a percentage of cost Fixes only the percentage Shared Owner carries more of the cost risk
The cost-risk spectrum

What makes it a contract

Step back from the money. What makes an agreement a contract at all? A contract is a promise a court will enforce, and before it enforces anything, a court wants to see five things:

  • Offer: one party proposes definite terms.
  • Acceptance: the other party agrees to those terms.
  • Consideration: each side gives something of value. That's what separates a deal from a favor. This isn't rule C.2's "valuable consideration," which means a gift or commission to win work.
  • Competent parties: each side is legally able to agree, which generally rules out a minor or someone a court has found incapacitated. This has nothing to do with engineering competence.
  • Lawful purpose: no court will enforce a deal to do something illegal.

That's the whole list. Anything else, however official it looks, is something people add around a contract, not part of what makes one.

Checkpoint
1 of 3

Which of these are not required for a valid contract?

A.
Consideration
B.
A written document
C.
Notarization
D.
Competent parties
E.
A lawful purpose
F.
An engineer's seal
G.
A performance bond

When the promise breaks

A breach is a failure to do what the contract promised. Courts usually answer with money, and one breach shows the two main kinds. A contractor walks off a half-built store, and the owner has to pay a replacement $60,000 more than the original price. That's the direct loss of the bargain, and money to cover it is compensatory damages, enough to put the owner where the contract would have. The store then opens four months late and loses $90,000 in sales. That's a knock-on loss, coming from what the owner meant to do with the building rather than from the work itself, and money for it is consequential damages.

Sometimes money won't do. If a seller backs out of selling the one parcel a pump station has to sit on, no damages can buy another. So a court can order specific performance: do what you promised. Courts keep that for one-of-a-kind things like land, and rarely use it to make anyone finish building.

Who decides all this? There are three routes.

Three ways to resolve a dispute
MethodWho decidesResult
MediationThe parties, with a mediator's helpNonbinding
ArbitrationA private arbitratorBinding
LitigationA judge or jury, in courtBinding, subject to appeal

A mediator helps you decide. An arbitrator decides for you. Litigation is the lawsuit, public and usually the slowest and costliest of the three.

Checkpoint
1 of 4

A roofing contractor walks off a nearly finished hotel. The owner pays a second roofer $40,000 more than the contract price, and the hotel opens two months late, losing $150,000 in room revenue. Which kinds of damages are these?

A.
Both amounts are compensatory
B.
The $40,000 is compensatory, and the $150,000 is consequential
C.
The $40,000 is consequential, and the $150,000 is compensatory
D.
Both amounts are consequential

Negligence: paying without a contract

Everything so far has been between people who signed something. The family on a collapsing balcony signed nothing with the engineer, and they can still make the engineer pay. That's negligence: a civil claim that you harmed someone by failing to use the care you owed them.

The Handbook uses the word only in the Model Law's grounds for disciplinary action, and never defines it. That's the board acting on your license. A negligence claim is about who pays, and one error can lead to both.

A claim has to prove four things, and they work like a chain.

Duty Did the engineer owe this person care? Breach Did the work fall below the standard of care? Causation Did that breach cause the harm? Damages Is there real loss or injury? All four: the claim succeeds. Any one missing: it fails.
The four links of a negligence claim

Duty is usually the easy link: you owe care to your client and to anyone your work could foreseeably hurt. Breach is where the standard of care goes to work, and here it means falling short of that care, not breaking a contract's promise.

The last two are the ones people forget. Your error has to be what caused the harm, and there has to be harm.

Worked Example The beam caught in time
1 of 4

You design a floor beam for a clinic and forget the partition load, which any competent engineer would include. A fabricator's detailer questions the size, and you correct the design and reissue it before any steel is ordered, at no cost to anyone. The owner hears about it, is furious, and sues for negligence. Would the claim succeed?

How far it reaches you

One more question. A beam fails, and people die. A claim will name the firm, and it may well reach individuals too. How far?

You know part of the answer already. The Handbook's definition of responsible charge ends with "Accept full responsibility for the work," and that's as far as it goes on the subject. For the rest, compare three engineers, each at a different firm where this has happened.

  • The salaried engineer who sealed the beam. She works for a corporation and owns none of it, so the firm's debts aren't hers. But the beam is her own work, and she can be held liable for it personally. The corporate name doesn't stand between her and her own negligence.
  • The general partner who never saw the beam. Another partner handled that job. But a partnership has no wall between the business and its owners, so the firm's debt is his debt too.
  • The shareholder who never saw the beam. She also owns part of her firm and also never touched the job, but her firm is a corporation. That wall keeps the firm's debts from reaching her.
Checkpoint

An engineer sealed the design of a structural member that failed and caused deaths. Which of these bear on the engineer's individual liability?

A.
Liability insurance carried by the firm
B.
The firm's form of ownership
C.
The engineer's role on the project
D.
Insurance carried by the steel supplier
E.
Insurance carried by the contractor
F.
The engineer's ownership position in the firm

Recap

  • Every contract type answers one question: who pays when the work costs more than expected? What's fixed, the contractor lives with, and what's left open, the owner pays for. So the contractor carries the most cost risk under lump sum, and the owner under cost plus a fee.
  • Cost plus a fee suits an undefined scope or a fast-tracked project. Unit price suits well-defined unit items with uncertain quantities, with the quantity risk on the owner. Cost plus a percentage rewards spending, and a fixed fee or a guaranteed maximum price limits the owner's exposure.
  • A valid contract needs offer, acceptance, consideration, competent parties, and a lawful purpose, but not writing, notarization, a seal, or a bond.
  • For a breach: compensatory damages for the direct loss, consequential damages for knock-on losses, and specific performance when money won't do. Mediation is nonbinding, arbitration is binding, and litigation goes to court.
  • Negligence needs duty, breach of the standard of care, causation, and damages, so an error that harms no one won't support a claim. Individual liability turns on the firm's form of ownership, the engineer's ownership position, and their role on the project, not anyone's insurance. A corporation doesn't shield you from your own negligence.