Time Rate of Consolidation

Clay settles as fast as water can escape it, and halving the drainage path makes it four times faster.

Before this Lesson

The distribution center in Consolidation Settlement will settle 8.5 in under its 6 ft of fill. The owner's next question is one the settlement equation can't answer: when can the floor slab go down?

It depends on what lies under the clay. If the boring finds sand, 90 percent of the settlement is over in about 2.3 years. If it finds rock, the same clay under the same fill needs more than 9 years. Nothing about the clay changed, only how far its water has to travel.

The settlement waits for the water

Recall from Changing Effective Stress what happens the day a fill goes onto saturated clay. The water in the pores can't get out of the way, so it carries the whole new load as excess pore pressure, and σ′\sigma' hasn't changed yet. The clay compresses only as that water leaves, like Terzaghi's piston sinking only as fast as water leaks through its hole. So the rate of settlement is the rate at which water escapes.

The water escapes to the nearest boundary that drains: a layer of sand or gravel, or the ground surface. It can't flow into unfractured rock or a much tighter soil, so those boundaries count as impermeable. The drainage path HdrH_{dr} is the longest distance any of the clay's water must travel to reach a draining boundary.

Two-way drainage One-way drainage Sand Sand Clay H Hdr = H/2 Sand Rock Clay Hdr = H
The drainage path for a clay layer of thickness H

Adapted from the FE Reference Handbook, Different types of drainage with u₀ constant

With sand above and below, the clay drains both ways. Water in the upper half goes up, water in the lower half goes down, and the water with the farthest to go sits at mid-depth, so HdrH_{dr} is half the layer. With rock below, every drop has to go up, and the water at the bottom has to cross the whole layer, so HdrH_{dr} is the full thickness. The Handbook makes the same point in its sketches of the types of drainage, where a layer drained both ways is 2Hdr2H_{dr} thick.

Twice the path, four times the wait

Doubling the drainage path doesn't double the time. It quadruples it, because two things work against you at once.

First, the excess pore pressure is the push that drives the water out. Over a path twice as long, that push is spread over twice the distance, so the hydraulic gradient is half as steep, and by Darcy's law the water flows half as fast. Second, twice the path means twice as much clay draining toward each boundary, so twice as much water has to leave. Half the speed and twice the water: four times the wait.

The Handbook packs this square law into one dimensionless number, the time factor, printed beneath its table of the degree of consolidation:

Tv=cvtHdr2T_v = \frac{c_v t}{H_{dr}^2}

Here tt is the time since the load went on, and cvc_v is the clay's coefficient of consolidation, which combines how easily water flows through it with how much it compresses. Its units are a length squared over a time, such as ft²/day, m²/yr, or cm²/s, and the Handbook leaves them to you: keep tt in the same time unit as cvc_v, and HdrH_{dr} in the same length unit.

Think of TvT_v as a clock that runs in the clay's own units of time, Hdr2/cvH_{dr}^2/c_v. Every layer, thick or thin, reaches the same degree of consolidation at the same TvT_v, so to find how long that takes, solve for tt:

t=TvHdr2cvt = \frac{T_v H_{dr}^2}{c_v}

Notice what isn't in it: the load. A heavier fill makes the clay settle more, but on the same schedule. The load sets how much, and the drainage path and cvc_v set how fast.

Checkpoint
1 of 2

A 12 ft layer of soft clay rests on a thick sand. Above it lies a stiff clay so much tighter that it can be treated as impermeable. What is the soft clay's drainage path?

A.
6 ft
B.
12 ft
C.
24 ft
D.
There is none, because the top can't drain

Reading the time factor table

The time factor is the clock reading, and the Handbook's table turns it into progress. UU, the average degree of consolidation, is the fraction of its ultimate settlement the layer has reached, which is also the fraction of its excess pore pressure that has drained away, averaged over the layer. The table, Variation of time factor with degree of consolidation, lists TvT_v for every whole percent of UU. Its values come from Terzaghi's theory for an excess pore pressure that starts out the same at every depth, as under a widespread fill. Here are a few of its rows:

Time factor TvT_v for selected values of UU
U (%)TvT_vU (%)TvT_v
100.00785600.286
200.0314700.403
300.0707800.567
400.126900.848
500.197951.129

Adapted from the FE Reference Handbook, Variation of time factor with degree of consolidation

100%: approached, never reached If U grew in step with time 0 0.2 0.4 0.6 0.8 1.0 1.2 0 20 40 60 80 100 Time factor, Tv Average degree of consolidation, U (%) U = 50%, Tv = 0.197 U = 90%, Tv = 0.848
Consolidation starts fast and finishes slowly
The curve plots the Handbook's table. The dashed line is what you'd get if UU grew in proportion to time.

Plot the table and you can see how consolidation goes. It starts fast, because the water near the boundaries has only a short way to travel, and half the settlement is done by Tv=0.197T_v = 0.197. Then it slows, because the water that's left is deep in the layer and the pressure pushing it out has faded. Reaching 90 percent takes until Tv=0.848T_v = 0.848, more than four times as long, and 100 percent never quite arrives, which is why questions ask about 90 or 95 percent.

So UU is not proportional to time. Early on it's the square law again: going from 30 to 60 percent takes four times the time factor, 0.286 against 0.0707.

Now the Hook. The 20 ft clay has cv=0.10c_v = 0.10 ft²/day. With sand below it as well as above, it drains both ways and Hdr=10H_{dr} = 10 ft, so 90 percent takes

t=0.848(10)20.10=848 days≈2.3 yrt = \frac{0.848(10)^2}{0.10} = 848\ \text{days} \approx 2.3\ \text{yr}

With rock below, Hdr=20H_{dr} = 20 ft. The time factor for 90 percent is still 0.848, and the time is four times as long: 3,392 days, or 9.3 years.

Checkpoint

An 8 m layer of clay lies on a dense gravel, with a sand above it, and has cv=2.0c_v = 2.0 m²/yr. How long after a widespread fill is placed will the clay reach 50 percent consolidation?

yr

How far along is it?

Most questions want a settlement, not a percent. The Handbook writes the settlement reached at a time as

ST=UAV SULTS_T = U_{AV}\,S_{ULT}

where SULTS_{ULT} is the ultimate settlement, the ΔH\Delta H you computed in Consolidation Settlement, and UAVU_{AV} is the average degree of consolidation, the table's UU as a decimal. From an elapsed time, the chain runs t→Tv→U→STt \to T_v \to U \to S_T. When TvT_v falls between the rows above, interpolate; on the exam, the Handbook's full table lets you read UU to the nearest percent.

Worked Example The distribution center after one year
1 of 2

The Hook's clay drains both ways, with Hdr=10H_{dr} = 10 ft and cv=0.10c_v = 0.10 ft²/day, and its ultimate settlement is 8.5 in. How much has it settled one year after the fill goes on?

Some questions run the chain backward: when will the layer have settled a given amount? Divide the settlement by the ultimate to get UU, read TvT_v from the table, and solve for tt. Don't scale the time in proportion to the settlement; the curve above shows why that fails.

Checkpoint

A 16 ft clay layer has sand above it and rock below, with cv=0.15c_v = 0.15 ft²/day. Its ultimate settlement under a new embankment is predicted to be 10 in, and paving can start once 8 in of that has occurred. How many days after the embankment is built can paving start?

days

Measuring the coefficient of consolidation

cvc_v is measured in the same consolidation test that gives CCC_C. A thin specimen, about an inch or 20 to 25 mm thick, sits between two porous stones, so it drains top and bottom, like the left panel of the drainage figure. Its HdrH_{dr} is half its thickness. For a load increment, the lab records settlement against time and reads off the time to 50 or 90 percent consolidation, t50t_{50} or t90t_{90}. The Handbook doesn't describe the test, but its time factor equation, solved for cvc_v, is all you need:

cv=TvHdr2t,e.g. cv=0.197 Hdr2t50c_v = \frac{T_v H_{dr}^2}{t}, \qquad \text{e.g. } c_v = \frac{0.197\,H_{dr}^2}{t_{50}}

If you only need the field time for the same UU, you can skip cvc_v. Same clay and same UU mean the same TvT_v, so the time scales with the square of the drainage path:

tfieldtlab=(Hdr, fieldHdr, lab)2\frac{t_{field}}{t_{lab}} = \left(\frac{H_{dr,\,field}}{H_{dr,\,lab}}\right)^2

Watch the units. Lab times come in minutes, with paths in inches or millimeters; field times come in years, with paths in feet or meters.

Worked Example From the lab to the field
1 of 3

A 1.0 in specimen of clay, drained top and bottom, reaches 50 percent consolidation in 12 min. Find cvc_v in ft²/day, then the time for a 12 ft layer of the same clay, between sand layers, to reach 90 percent consolidation.

Shortening the path

A thick clay can take longer than any project can wait. A 40 ft layer of the Hook's clay, drained top and bottom, has Hdr=20H_{dr} = 20 ft and needs 9.3 years to reach 90 percent. The square law says where to attack: the path.

Wick drains, also called prefabricated vertical drains, are flat plastic cores wrapped in filter fabric, pushed down through the clay in a grid a few feet apart, with a sand blanket on top to carry the water away. The water no longer has to travel 20 ft up or down. It moves sideways a few feet to the nearest drain, then up the drain. Cut the path from 20 ft to a few feet, and because time goes with its square, years become months. (The exact analysis of flow toward a drain is beyond the FE exam; the shorter path is the idea.)

Without drains With wick drains Fill Sand Sand Clay H/2 Fill Sand Sand Clay Wick drain s ≈ s/2
Wick drains turn a long vertical path into a short sideways one
ss is the spacing between drains.

What the drains don't change is the ultimate settlement. That comes from CCC_C, HH, e0e_0, and the stresses, and a drain alters none of them. The clay settles just as much, only sooner. Drainage changes how fast a clay settles, never how much.

Preloading attacks the problem from the other side: it lets the settlement happen before there's anything to damage. A fill goes on the site before construction, often heavier than the future structure, which makes it a surcharge. It stays until the clay has settled as much as the structure would make it settle, and then it's removed and the structure is built. Drains and a preload often work together, the drains making the preload's wait months instead of years. The Handbook doesn't mention either one, so questions about them test the ideas rather than a formula.

Checkpoint
1 of 2

Without drains, a clay layer under a planned fill is predicted to settle 12 in, with 90 percent of it reached in 8 years. Wick drains are then added to the design at close spacing. Which prediction is most reasonable now?

A.
Less than 12 in, with 90 percent reached in months
B.
12 in, still taking 8 years, because the clay's cvc_v hasn't changed
C.
12 in, with 90 percent reached in months
D.
Less than 12 in, still taking 8 years

Recap

  • Clay settles only as its excess pore water escapes. The drainage path HdrH_{dr} is the longest trip to a draining boundary: half the layer with sand on both sides, the whole layer with rock or another impermeable boundary on one side. A lab specimen drains both ways.
  • Tv=cvt/Hdr2T_v = c_v t/H_{dr}^2, so the time goes as Hdr2H_{dr}^2: halving the path cuts the time to a quarter, and going from two-way to one-way drainage, or doubling the layer's thickness, quadruples it.
  • The Handbook's table gives UU for each TvT_v, and ST=USULTS_T = U S_{ULT}. UU is not proportional to time: 50 percent at 0.197, 90 percent at 0.848.
  • For a stated settlement, take U=ST/SULTU = S_T/S_{ULT}, read TvT_v, and solve t=TvHdr2/cvt = T_v H_{dr}^2/c_v. From a lab test, cv=TvHdr2/tc_v = T_v H_{dr}^2/t, or scale the time by (Hdr, field/Hdr, lab)2(H_{dr,\,field}/H_{dr,\,lab})^2, with consistent units.
  • Wick drains shorten the path and speed consolidation without reducing the ultimate settlement. A preload makes the settlement happen before construction.