Equipment Production
A machine's output is how much it carries per trip times how many trips it makes.
Before this Lesson
A wheel loader with a 5 yd³ bucket can scoop, back out, dump into a truck, and come back in 40 seconds. That's 90 buckets an hour, or 450 cubic yards an hour on paper. At the end of the week, the cross sections of the cut say it moved 270 bank yards an hour, 60% of the paper number. Nothing broke, and the operator was good. The bucket came up a little short of heaped, the loader didn't work every minute of every hour, and the yards in its bucket were loose ones. Each of those is one multiplication.
Carried per trip, times trips per hour
From Earthwork Volume States and Hauling: soil in the ground is measured in bank cubic yards (BCY), and once it's dug, the same soil takes more room as loose cubic yards (LCY). With the swell written as a decimal,
Label every volume with its state, and the two can't mix.
Every earthmover works in cycles. An excavator digs, swings, dumps, and swings back; a loader scoops, backs out, dumps, and returns; a dozer pushes its blade load and reverses; a scraper loads, hauls, spreads, and comes back. Whatever the machine, its hour is a string of repeated trips, so its production is what it carries per trip times the number of trips.
The trips come from the cycle time. A machine that takes minutes per cycle fits cycles into an hour. Bucket cycles are often given in seconds, and then the cycles per hour are 3,600 seconds over the cycle: the 40-second loader manages 3,600/40 = 90.
What it carries is the payload, . A bucket's rated capacity is its heaped volume, and a real pass doesn't always come up heaped. When a question gives a bucket fill factor, the payload is the capacity times that factor: 5 yd³ at a fill factor of 0.90 is 4.5 LCY a pass.
The third factor is the one people forget. Watch any machine for an hour and you'll see it stop: it walks to a new face, the operator clears a boulder or talks with the grade checker, someone takes a break. The job efficiency, , is the fraction of each hour spent actually working. Questions often state it as an -minute hour: a 50-minute hour means , and a 45-minute hour means 0.75. Efficiency doesn't make the cycles slower. It takes away minutes to run them in. Put the three together, with for the hourly production:
With an -minute hour, is just , so the same line reads : the working minutes over the cycle time are the cycles the machine really completes. Use one form or the other. Dividing 50 minutes by the cycle and then multiplying by 0.833 charges for the lost minutes twice.
Last comes the state. A bucket, blade, or bowl carries soil that's been dug, so is in LCY, and so is . When a question wants bank yards, convert the hourly production once, at the end: divide by , or multiply by the load factor. Here's the Hook's loader, one factor at a time:
The Handbook prints no production formulas, so a question gives every payload, cycle time, and efficiency. The method is the same for all four machines. A dozer's or a scraper's cycle includes travel, timed the way the next section times a truck.
Timing a haul truck
A haul truck follows the same bookkeeping, except that its cycle time isn't given. You build it by following one truck around the loop:
- Spot: back into position beside the loader.
- Load: wait while the loader fills the bed.
- Haul: drive to the fill, loaded.
- Dump: dump the load and turn around.
- Return: drive back, empty.
Spotting, loading, and dumping are fixed times the question states. Hauling and returning are travel, distance over speed, and each leg gets its own speed. A loaded truck is slower than an empty one, so the trip back over the same road is quicker.
Speeds come in miles per hour, and distances often in feet. A mile is 5,280 ft and an hour is 60 minutes, so 1 mph is 88 ft/min, a factor the Handbook's Units and Conversion Factors table lists. A leg's time in minutes is then
The cycle time is the sum of all five parts. The truck's trips per hour are the working minutes over that cycle, , and its production is the payload times the trips. Leave the trips as a decimal. 3.6 trips an hour is an average, and over a 10-hour shift it's 36 loads.
Working backward from a target
Sometimes the production is the given, and the question asks what a machine needs to deliver it: the smallest payload, or the longest cycle time. It's the same equation with a different unknown, and the cleanest way through is to count cycles. The target production over the payload is how many cycles the machine must complete each hour, and those cycles have to fit into the working minutes.
Say a scraper must move 200 LCY/hr on a 50-minute hour with a 2.5-minute cycle. It completes 50/2.5 = 20 cycles an hour, so each has to carry 200/20 = 10 LCY. Turn it around, and a 10 LCY scraper needs 20 cycles from its 50 minutes, so no cycle can take longer than 2.5 minutes. Solving for each unknown says the same:
Two things to watch. The target and the payload have to be in the same state, so a target in BCY/hr gets swelled to LCY/hr before it meets a bucket in LCY. And the answers are limits: the payload is a minimum, so you'd pick the next bucket size up, and the cycle time is a maximum, so any faster cycle works too.
What a longer haul or a slower hour costs
Questions also ask which way production moves when one input changes, and answers the two common cases at a glance.
Efficiency sits in the numerator, on its own. Lose working minutes and production falls in proportion to them, while the cycle time doesn't change at all: the truck drives no slower, and the loader fills it just as fast. There are only fewer minutes to fill with cycles.
A longer haul works through the denominator, and only partly. Doubling the distance doubles the haul and return times, but spotting, loading, and dumping take as long as they did. So the cycle grows by less than double, and production falls by less than half. A scraper's longer haul or a dozer's longer push works the same way, since only the travel grows. Here's the worked example's truck with its haul doubled:
A loader's or an excavator's own cycle has no haul in it. A longer haul reaches it only through whether enough trucks keep coming, and that's the subject of Fleet Balancing and Equipment Cost.