Fleet Balancing and Equipment Cost
A fleet moves only as fast as its slowest link.
Before this Lesson
A loader on a highway cut fills a haul truck in 3 minutes. Each truck then spends 9 minutes hauling, dumping, and driving back, so it's ready for another load every 12 minutes. The contractor has three trucks. Watch the loader for a while, and you'll see it fill all three, then sit with its bucket on the ground for 3 minutes until the first one is back. Hire a fourth truck, and the job moves a third more dirt every hour. Hire a fifth, and it moves exactly as much as it did with four, while the fifth driver spends the day in line.
Two machines, one chain
From Equipment Production: a haul truck's cycle is spot + load + haul + dump + return, and a machine's hourly production is
with payload , cycle time in minutes, and working minutes in each hour (50 for a 50-minute hour). Buckets and truck beds carry dug soil, so and are in LCY. Divide by for bank yards.
A loader and its trucks form a chain. The loader can't load soil faster than trucks arrive to take it, and the trucks can't haul more than the loader puts in them. To see how the two fit together, you need one time from each machine.
The first is the loading time, : how long the loader takes to fill one truck. It fills the truck a bucket at a time, so is the number of bucket passes times the loader's cycle time, and the passes are the truck's capacity over the bucket's payload. A 15 LCY truck under a 3 LCY bucket takes 5 passes, and at 36 seconds a pass, minutes.
The second is the truck's cycle time, , built from its five parts, and the minutes under the loader are one of them. A question often gives the other four and leaves for you to work out and add. Here is the Hook's loader over two truck cycles:
While one truck goes through its 12-minute cycle, the loader has time to fill trucks. So the number of trucks that keeps a loader busy is the number of loading times that fit into one truck cycle:
On a real job, is rarely a whole number. Say it comes out 5.6. With five trucks, the loader waits for part of every cycle. With six, it never waits, and each truck waits a little in turn instead. Keeping the loader busy takes six, so the count rounds up.
The slower link sets the pace
Each link in the chain has a production of its own. If a truck is always waiting, the loader puts one truckload into a truck every minutes. Each truck delivers its once every minutes, and trucks deliver times as much. What the loader loads, the trucks carry, so the fleet moves whichever is smaller:
Divide the trucks' production by the loader's, and almost everything cancels, leaving . The trucks are the slower link when is less than , and the loader is when it's more: the truck count from the last section, seen from the other side.
Give the Hook's trucks a 15 LCY payload and the job a 50-minute hour. Each truck hauls LCY/hr, and the loader can load LCY/hr, the same as its 3 LCY bucket on a 36-second cycle, . Add trucks one at a time and watch the fleet:
A fleet with too few trucks is undertrucked: the trucks limit production, and the loader waits. A fleet with too many is overtrucked: the loader limits, and trucks wait in line to be loaded. Either way, the waiting machine is still being paid for by the hour.
Two pieces of bookkeeping keep the comparison honest. Both rates must be in the same volume state: a bucket and a truck bed both carry loose soil, so take the smaller rate in LCY and convert it to bank yards once, if the question asks. And the job efficiency scales both rates alike, so it can never change which one is smaller, and it goes in once. The Handbook prints none of this Lesson's relations, so a question gives every payload, cycle, and rate you need.
Time is quantity over production
Once you know what a fleet produces, the schedule follows from one division:
Yards divided by yards per hour leaves hours, and the working hours in a day turn hours into days. The quantity and the production have to be in the same state, and they often aren't, because a cut is measured in the ground and a fleet's production in its trucks.
Put the Hook's four-truck fleet, 250 LCY/hr, on a cut of 30,000 BCY that swells 25%. In loose yards the cut is LCY, and hours is 15 ten-hour days.
A deadline runs the same division the other way. The quantity over the hours available is the production the job needs, and that over what one machine or fleet produces is how many it takes. To finish the cut in 10 days, the job needs LCY/hr, or fleets. Half a loader doesn't exist, and one fleet would finish late, so the job needs 2 fleets, each a loader with its four trucks. A count of working days rounds up too, since the fleet is on site for the last partial day. Crews are counted the same way: 12,000 ft² of forms set in 5 days takes 2,400 ft² a day, and at 1,500 ft² per crew a day, that's 1.6 crews, so 2. Crew Costs, Task Duration, and Markups carries the same division into crew costs.
Cost per cubic yard
Equipment is rented by the hour, but earthwork is paid for by the yard. To compare machines on the yard's terms, divide what each costs in an hour by what it moves in that hour:
An $80/hr loader that moves 160 LCY/hr costs $0.50 a yard. A $120/hr loader that moves 300 LCY/hr costs $0.40, less per yard though it costs half again as much to rent. A bigger machine rents for more and moves more, and only the ratio says which grows faster. Some questions ask for the highest production per dollar instead, hourly production over hourly cost. That's the same ratio upside down, so the same machine wins. A machine's rental rate or its production alone is half the ratio, and can point to the wrong machine.
When the fleet changes
For a whole fleet, the hourly cost is everything on the clock, the loader plus every truck, and the production is the fleet's. Price the Hook's fleet with the loader at $150/hr and each truck at $90/hr:
| Trucks | Cost ($/hr) | Production (LCY/hr) | Unit cost ($/LCY) |
|---|---|---|---|
| 3 | 420 | 187.5 | 2.24 |
| 4 | 510 | 250 | 2.04 |
| 5 | 600 | 250 | 2.40 |
While the fleet is undertrucked, an added truck brings its full 62.5 LCY/hr along with its $90, and the loader's $150 is spread over more yards, so the unit cost falls. Once the fleet is overtrucked, an added truck brings $90 and no yards, so the unit cost only rises. The cheapest yard comes from a balanced fleet. When isn't a whole number, the best fleet is one of the two truck counts on either side of it, so price both.
A longer haul upsets the balance from the trucks' side. It stretches and leaves alone, since the loader fills a truck just as fast as before, so grows and a balanced fleet becomes undertrucked. The loader starts waiting, production falls to what the trucks can haul, and the unit cost climbs, because every machine is still on the clock. More trucks, as many as the new calls for, bring the loader back to full work. An overtrucked fleet has trucks to spare, so it can take a little more haul before the trucks become the slower link.