Earthwork Volume States and Hauling
Dig up a cubic yard, and you'll haul more than a cubic yard.
Before this Lesson
- Cut, Fill, Shrinkage, and Mass Haul · Surveying
A basement excavation measures 1,200 cubic yards on the plans, and the haul trucks carry 15 cubic yards each, so the dispatcher books 80 loads. Load 80 pulls away, and a fifth of the hole is still in the ground. The plans were right, and so were the trucks. The 1,200 yards were measured in the ground and the 15 in a truck bed, and dirt that has been dug takes more room than dirt that hasn't. This job needed 100 loads.
One weight, three volumes
From Cut, Fill, Shrinkage, and Mass Haul: the same soil has a bank volume in the ground, a loose volume once it's dug, and a compacted volume once it's rolled into a fill. Swell and shrinkage are both measured against the bank volume, unless a question says otherwise:
The shrinkage factor is . The grains' weight never changes, so the volumes in any two states are in the inverse ratio of their dry unit weights.
Digging doesn't make dirt, and rolling doesn't destroy it. Both only change how much air sits between the grains. So a batch of soil weighs the same in the ground, in the truck, and in the fill, and since weight is volume times unit weight,
Nearly everything in this Lesson comes out of that one line. Every conversion factor is a ratio of two unit weights, and the state with the lighter unit weight always takes the bigger volume.
A number like 1,200 yd³ means little until you know which state it's in, so construction writes the state into the unit: BCY for bank cubic yards, LCY for loose, and CCY for compacted. Label every volume with its state, and most of the mistakes in this Lesson can't happen. Each state has its place on a job:
- Excavation is in BCY. A hole computed from the plans, or ground surveyed before it's dug, measures soil that sat in the bank.
- Hauling is in LCY. A truck bed, a loader bucket, and a stockpile all hold soil that has been dug.
- Fill is in CCY. The plans give the finished embankment or pad, rolled to its final density.
Bank sits in the middle for a reason: swell and shrinkage are both percentages of the bank volume, so every conversion goes into or out of bank. The next sections walk each arrow. None of these conversions is in the Handbook, which prints no swell, load factor, or loose volume, so they're worth knowing cold.
From the ground to the truck
A 25% swell means each bank yard comes out of the ground as 1.25 loose yards. With the swell written as a decimal,
That's the Hook's arithmetic: 1,200 BCY × 1.25 = 1,500 LCY, and at 15 LCY a load, 100 loads.
To go back from the truck to the ground, you divide by the same 1.25. Its reciprocal has a name, the load factor:
At 25% swell, LF = 0.80: each loose yard in the truck came from 0.80 of a yard in the ground. The tempting shortcut is to multiply by , 0.75 here, and a round trip shows what it costs. 100 BCY swells to 125 LCY, and 125 × 0.75 = 93.75 BCY, so more than six yards vanished on the way back. The 25% was a percentage of the bank, not of the loose, and only dividing by 1.25 undoes it.
Counting truckloads is a division with one rule: round up. If the loose volume over the truck's capacity comes out to 64.1, the last tenth of a load still needs a truck, so it's 65 loads.
Unit weights, and a truck's two limits
Questions often skip the percentage and give unit weights instead, such as 3,000 lb/BCY in the bank and 2,400 lb/LCY loose. The weight line turns them straight into the factors:
Here, swell = 3,000/2,400 − 1 = 0.25, and LF = 2,400/3,000 = 0.80. The load factor is less than 1, so the lighter loose weight goes on top.
For the factors, either kind of unit weight works. The Handbook's Phase Relationships define the total unit weight , water included, and the dry unit weight , solids only. Digging and hauling don't add or remove water, so both give the same ratio between bank and loose. For a fill that's watered before it's rolled, use dry unit weights.
Unit weights matter for a second reason. A haul truck has two limits. Its heaped capacity is the loose volume its bed holds, heaped in a mound above the sides. Its rated payload is the weight its frame, axles, and tires are built to carry. A light soil fills the bed before it gets near the payload. A heavy soil reaches the payload with room still left in the bed.
So check both, and weigh the load with the total unit weight, because the truck carries the water too. A heaped load weighs its heaped capacity times . If that's under the payload, the bed limits each load. If it's over, the payload limits it, and each load holds the payload divided by . Payloads usually come in tons, and the Handbook's Units and Conversion Factors give the short ton as 2,000 lb.
Working back from the fill
A fill question runs the other way. The plans give compacted yards, and you need the bank yards to dig and the loose yards to haul. Shrinkage is a percentage of the bank volume too, so
where is the shrinkage factor. A soil fill always needs more yards dug than it holds. Multiplying by instead is the trap here, and it fails the same round trip: at 20% shrinkage, 100 BCY packs down to 80 CCY, and 80 × 1.20 = 96, four yards short of the bank you started with.
From bank, swell the volume to get the loose yards the trucks will carry. With percentages, there's no shortcut that skips bank. Adding the swell and shrinkage percentages, or swelling the compacted yards, applies a percentage to a volume it was never measured against.
Which way is bigger?
With three states and four arrows, it helps to have a check that needs no formula. For ordinary soil, the states line up by how much air they hold: loose has the most, then bank, then compacted, and the same weight takes the most room where there's the most air. So a factor that carries a volume toward a looser state is greater than 1, and one that carries it toward a denser state is less than 1. If a converted volume moves the wrong way, a factor is upside down.
Stockpiles stand at the angle of repose
Dump dirt in one spot and it builds itself a cone. Grains roll down the sides until the slope is just gentle enough for them to stay put, and that steepest stable slope is the soil's angle of repose, . Seen from the side, the pile is a triangle, with the height rising over the base radius at that angle:
The Handbook's Mensuration of Areas and Volumes gives a right circular cone's volume as , the same one third its Earthwork formulas print for a pyramid or cone. Substitute , and the volume depends on the radius alone, so you can solve for it:
With in hand, the base diameter is and the height is . The Handbook prints no stockpile formula, so these come from the geometry. Two things decide the inputs. A stockpile holds dug soil, so is a loose volume, and bank yards get swelled first. And the dimensions come out in feet only if goes in as cubic feet, at 27 ft³ per yd³.