Project Delivery and Contract Administration
Who designs, who builds, who pays, and who's protected if it goes wrong.
Before this Lesson
- Contracts and Professional Liability · Ethics and Professional Practice
A city is about to sign a $4.2 million contract for a new fire station. Before the first truck arrives, that contract has to answer questions nobody enjoys asking. Does one firm design the station and another build it? If the drawings and the specifications disagree, which wins? If the contractor goes broke halfway through, who finishes, and who pays the electrician? And if the station opens more than five weeks late, what does the city get?
Nearly every provision in a construction contract does one of two jobs. It puts a risk on a particular party, or it gives the owner a lever to get the work finished. Ask whose risk it is and who holds the lever, and most of these questions answer themselves. The Handbook prints none of this, so it's all yours to carry in, and the problem will give you any rate, date, or clause it needs.
Who signs with whom
The project delivery method decides how many contracts the owner signs, with whom, and when the builder comes aboard.
In design-bid-build (DBB), the owner hires a designer to finish the drawings and specifications, puts the complete design out for bids, and awards the construction contract, usually to the low bidder. The owner holds two separate contracts, and the phases run one after another. The designer and the contractor have no contract with each other, so the owner stands in the middle: if the drawings are wrong, the contractor's claim is against the owner.
Design-build (DB) closes that gap. The owner signs one contract with a single firm or team that designs and builds, so one party answers for everything, design errors included. And because the designer and the builder are on the same side, construction can start before the design is finished. The price is control: the designer now works for the builder, not the owner.
A contract type says how the price is set, and so who pays an overrun. A lump sum fixes the total, so the contractor pays. Unit price fixes the rate, and the owner pays for the quantity measured. Cost plus a fee pays actual cost plus a fee, so the owner pays. A guaranteed maximum price (GMP) is cost plus a fee with a ceiling, above which the contractor pays. For more, see Contracts and Professional Liability.
A construction manager (CM) can hold either of two very different jobs, and the difference is the words "at risk."
A construction manager at risk (CMAR) joins during design, advising the owner and its separately hired designer on cost, schedule, and buildability. When the design is far enough along, it commits to a guaranteed maximum price and builds the job, holding the trade contracts itself. If the work costs more than the GMP, the CM pays. That's the risk.
An agency construction manager is the owner's adviser, paid a fee the way the designer is. It estimates, schedules, and coordinates, but the owner signs the trade contracts, so an overrun is the owner's, and the agency CM carries no cost risk at all.
Each method trades something for something else, so the right one depends on what the owner wants most.
The documents that make up the contract
Some of the paper the designer assembles only runs the competition. The invitation to bid announces the job and when bids are due, and the instructions and bid form say how to bid. Once the contract is signed, what binds the parties are the contract documents.
| Document | What it holds |
|---|---|
| Agreement | The parties, the price, and the contract time |
| General conditions | Rights, duties, and procedures |
| Supplementary conditions | Changes to the general conditions |
| Specifications | Materials, workmanship, and quality, in words |
| Drawings | Locations, dimensions, and arrangement, in pictures |
The general conditions are usually a standard form covering how payments, changes, and claims work, and the supplementary conditions edit it for this job. A drawing can show a 6 in. slab in the right place, but it takes the specifications to say what concrete goes in it, how it's cured, and what tests it must pass.
After signing, before the contractor orders anything, it sends the engineer submittals: shop drawings, samples, cut sheets (a manufacturer's catalog pages), and material certifications (a supplier's statement that its material meets a standard). A submittal shows how the contractor plans to meet the requirements. It doesn't set them.
Sooner or later, two documents disagree: the drawings call for 3,000 psi concrete, and the specifications for 4,000 psi. Most contracts settle this in advance with an order-of-precedence clause, a ranked list in which the higher document governs. One common list runs agreement, supplementary conditions, general conditions, specifications, drawings, so the 4,000 psi would govern. But some contracts rank the drawings higher. On the exam, use the clause the problem gives you, not one from memory.
Bids and bonds
If the bidding documents need fixing while the job is out to bid, the owner issues an addendum to every bidder before bids are opened, so they all price the same job. Addenda become part of the contract.
On a lump-sum job, the lowest bid wins. On a unit-price job, the owner builds a bid tabulation: each unit price times the engineer's estimated quantity is an extension, and each bidder's extensions add up to its total.
| Item | Quantity | A, unit price | A, extended | B, unit price | B, extended |
|---|---|---|---|---|---|
| Excavation (yd³) | 18,000 | $7.50 | $135,000 | $9.00 | $162,000 |
| Pipe (ft) | 3,200 | $62 | $198,400 | $58 | $185,600 |
| Manholes (each) | 12 | $4,200 | $50,400 | $3,600 | $43,200 |
| Total | $383,800 | $390,800 |
Bidder B is cheaper on two of the three items, and its unit prices add up to less. Neither matters. A sum of unit prices adds dollars per cubic yard to dollars per manhole, which means nothing, and B's $600 edge per manhole buys only 12 of them, while A's $1.50 edge applies to 18,000 yd³. Bidder A is low, at $383,800.
Now the owner has a low bidder, and some worries. What if it backs out before signing, or starts the job and goes broke? The answer is a surety bond, which is less like insurance than like a co-signer on a loan. The contractor, the principal, makes a promise to the owner, the obligee. The surety, a bonding company, guarantees it: if the contractor fails, the surety makes the promise good, and then it's entitled to every dollar back from the contractor. The bond protects the owner, not the contractor.
A construction job uses three bonds, one for each way to fail:
- A bid bond guarantees that if this bidder wins, it will sign the contract and furnish the other two bonds. If it walks away, the surety pays the owner its loss, usually the gap to the next bid, up to the bond's amount.
- A performance bond guarantees the owner that the work will be completed as the contract requires.
- A payment bond guarantees that the contractor will pay its subcontractors, laborers, and suppliers.
Changes after signing
No set of drawings is perfect. When the contractor finds a duct drawn straight through a beam, it sends a request for information (RFI), a written question, and the engineer's answer clarifies what the contract already requires.
A change order is a written amendment, signed by the owner and the contractor after award, that changes the scope, the price, or the time, and it's the only way any of them moves. Asking isn't changing: an RFI clarifies, and a change order changes. The award is also the line between a change order and an addendum, which changes the bidding documents before bids are opened.
Over a job, change orders pile up. The revised contract sum is the original plus the approved additions, minus the approved deductions, and the revised completion date is the original plus the days the approved change orders add. A proposed change order counts for nothing until it's approved. To price one, find the direct cost of the changed work, quantities times unit costs, and add the markup the contract allows. A bid stacks several markups, which is the business of Crew Costs, Task Duration, and Markups.
Getting paid as the work goes in
A contractor is paid monthly, in progress payments, for the work in place to date. On a unit-price job, that's each item's measured quantity to date times its unit price. On a lump-sum job, it's each line of the schedule of values, the contract price split by part of the work, times its percent complete.
The owner holds back retainage, a stated percentage of the work in place to date, until the job is done. That's its lever over the finish: a contractor with a tenth of the job's value in the owner's drawer has every reason to come back for the last repairs. The earlier payments already had their retainage taken out, so everything works in totals to date, with the retainage rate:
So take retainage on the whole amount to date, not just this month's work, and subtract what was actually paid.
Finishing late
When the fire station opens late, the city pays for it: rented space for the trucks, an inspector's extra weeks, an old station kept running. Those costs are real but hard to prove, so the contract settles them up front. Liquidated damages (LDs), the owner's other lever over the finish, are a daily amount, agreed at signing, that the contractor owes for each day it finishes past the contract completion date. They must be a reasonable estimate of the owner's cost, not a penalty set to punish, which courts won't enforce, and they aren't a charge for damaged work.
They count only the days that are the contractor's own. An approved time extension moves the completion date, and LDs count from the new date until, usually, substantial completion. The fire station's contract set a completion date of September 30 and LDs of $1,800 per day. The city approved 14 days of extensions, moving the date to October 14, and the station reached substantial completion on November 5.
Charging all 36 days from September 30 would bill the contractor for 14 days the city had already excused.