Cut, Fill, Shrinkage, and Mass Haul

Dirt changes size when you dig it up, and again when you pack it down.

Before this Lesson

A grading plan for a new lot says to push a knoll at the back into a hollow at the front. The contours say the knoll holds 3,000 cubic yards and so does the hollow, so on paper the job balances. Then the dozers go to work, and the hollow comes up about 300 yd³ short. Nobody mismeasured. The knoll was measured as it sat in the ground, the hollow as the packed fill it will hold, and a yard of one isn't a yard of the other. Keeping those yards straight is the whole game, from one hollow to a mile of road.

One dirt, three volumes

Dig a hole and try to put all the dirt back. You can't: there's a mound left over, because the dirt came out with air worked in between the grains. Now run a roller over that mound long enough, and it can sink below the rim of the hole. Nothing was added and nothing was lost. The same grains sat in three different volumes, and earthwork gives each one a name:

  • Bank volume is the dirt in place, undisturbed, as the ground holds it. Cut is measured this way.
  • Loose volume is the dirt once it's dug, sitting in a bucket, a truck, or a pile, fluffed up with air.
  • Compacted volume is the dirt placed and rolled into a fill. Compaction usually packs it tighter than the ground ever did, so it takes less room than it did in the bank.
bank in place 1.00 yd³ γD = 108 lb/ft³ loose dug 1.25 yd³ γD = 86.4 lb/ft³ compacted in the fill 0.90 yd³ γD = 120 lb/ft³ dig compact same WS = 2,916 lb of solids in each
The same grains in three states

Going from bank to loose is swell, and going from bank to compacted is shrinkage. Both are measured against the bank volume:

percent swell=Vloose−VbankVbank×100percent shrinkage=Vbank−VcompactedVbank×100\begin{aligned} \text{percent swell} &= \frac{V_{\text{loose}} - V_{\text{bank}}}{V_{\text{bank}}} \times 100 \\[4pt] \text{percent shrinkage} &= \frac{V_{\text{bank}} - V_{\text{compacted}}}{V_{\text{bank}}} \times 100 \end{aligned}

The dirt in the figure swells 25% and shrinks 10%. The shrinkage factor is the fraction of the bank volume that's left once it's compacted, here 0.90:

SF=VcompactedVbank\text{SF} = \frac{V_{\text{compacted}}}{V_{\text{bank}}}

Not every problem measures from the bank, though. Some quote shrinkage against the compacted volume, where 10% shrinkage makes the bank 1.10 times the compacted volume, so read which basis a question uses. Loose volume is what a truck carries, and it comes back with load factors in Earthwork Volume States and Hauling. Here, the action is between bank and compacted.

Where does a factor like 0.90 come from? Weigh the grains. The Handbook's Phase Relationships define dry unit weight as the weight of solids over the total volume they occupy, air and water included:

γD=WSV\gamma_D = \frac{W_S}{V}

Digging and rolling move air and water around, but the grains stay put, so WSW_S never changes. That makes V=WS/γDV = W_S/\gamma_D, and the same dirt's volumes in any two states are in the inverse ratio of their dry unit weights:

SF=VcompactedVbank=γD,bankγD,compacted\text{SF} = \frac{V_{\text{compacted}}}{V_{\text{bank}}} = \frac{\gamma_{D,\text{bank}}}{\gamma_{D,\text{compacted}}}

In the figure, that's 108/120 = 0.90. The denser state always gets the smaller volume, which is the quickest check on a ratio: if a fill that's denser than its bank comes out with more volume, the ratio is upside down. Unit Weights of Soil treats dry unit weight fully, but this one definition is all you need here.

Slicing a pond or a knoll by its contours

Average end area, from End Areas and Volumes, doesn't care which way you slice. Along a road, the slices stand up across the centerline. A pond or a knoll comes already sliced, lying down: each contour on the map encloses an area at one elevation, and neighboring contours sit one contour interval apart. Take two neighboring contour areas as the ends and the interval hh as the length, and each slab is a reach on its side:

V=h(A1+A22+A2+A32+⋯ )V = h\left(\frac{A_1 + A_2}{2} + \frac{A_2 + A_3}{2} + \cdots\right)

Every slab is one interval thick. Using the knoll's whole height as the length treats a stack of slabs as one fat slab with only the top and bottom areas, and that misses the shape in between.

plan 100 102 104 106 A2 = area inside the 102 contour side view A1 A2 A3 A4 102 104 106 pad grade, 100 h h = contour interval
A knoll sliced at its contours
The vertical scale is stretched so the slabs are easy to see.

Which state you've measured depends on what you sliced. A knoll's contours outline dirt sitting in the ground, so a knoll cut down to a pad gives bank volume. A pond's contours outline a hole, and the fill packed into it takes exactly that space, so a pond to be filled gives compacted volume. The Handbook has no contour method of its own. It's the Earthwork formulas' average end area, with the interval as LL. If a knoll's top rises to a point above its last contour, that cap is the Handbook's Pyramid or Cone: one third of the top contour's area times the cap's height.

Worked Example Filling a hollow
1 of 2

A hollow on a building site will be filled to elevation 250 ft. The areas inside its contours are below, and its bottom is flat at 244 ft. The fill will be compacted to a dry unit weight of 117 lb/ft³, from borrow soil that weighs 104 lb/ft³ dry in the bank. Find the compacted volume of fill, then the bank volume to dig.

Areas inside the contours
Contour (ft)Area (ft²)
25012,400
2488,600
2465,200
244 (flat bottom)1,800

Slice it the way it was measured

Every volume in this topic is the same move: cut the dirt into slices you can measure, then add them up. How the ground was measured decides the slicing:

  • Along a route, such as a road, a ditch, or a levee, the crew takes cross sections at stations, so use average end areas, with the length from the stations.
  • A pond, depression, or knoll mapped by contours takes contour areas, with the contour interval as the length.
  • A borrow pit is staked as a grid of squares, with the ground shot at every corner before and after digging. Each square is a short column of dirt: its area times the average of its corner cuts.
  • Wherever a section pinches down to nothing, as at a cut-fill transition, the solid is a pyramid, V=AL/3V = AL/3.

The Handbook's Earthwork formulas print average end area and the pyramid; the grid method is the same slice-and-add idea.

Checkpoint

Which of these pair a job with the method that fits it?

A.
A lot to be lowered, with the ground shot at the corners of 25 ft squares before and after: contour areas
B.
A drainage channel, cross-sectioned every 50 ft along its length: average end areas between the sections
C.
A fill that thins to nothing where the road passes into cut: average end area with one end of zero
D.
An old farm pond to be filled to grade, mapped with 1 ft contours: contour areas with a 1 ft length

Cut and fill in the same yards

Back on a road, the mismatch between the knoll and the hollow hides in every table. Cut end areas are drawn on the ground before it's dug, so cut volumes are bank yards. Fill end areas are drawn on the finished embankment, so fill volumes are compacted yards. Subtracting one from the other mixes two currencies.

So convert first. Each compacted yard of fill takes 1/SF1/\text{SF} bank yards to build, so the bank volume a fill needs is

Vfill, bank=VfillSFV_{\text{fill, bank}} = \frac{V_{\text{fill}}}{\text{SF}}

and the net is the cut minus that. A plus result is an excess, dirt to haul off and waste. A minus result is a shortage, to be made up from borrow.

The Handbook's Earthwork formulas cover this in one line: shrinkage is handled "by increasing fill at each station by the shrinkage factor." They don't say how. With SF defined as compacted over bank, below 1, increasing means dividing. If a question hands you a factor above 1 for the fill, such as 1.10, it's quoting bank over compacted, so multiply. Either way, the adjusted fill comes out bigger than the fill.

Worked Example Two reaches of side-hill road
1 of 2

A road in side-hill cut and fill has these end areas, and its fill has a shrinkage factor of 0.90. Find the cut and fill volumes, and the net excess or shortage.

End areas
StationCut (ft²)Fill (ft²)
15+0015030
16+00140120
17+00110240

A running balance

A net total says whether a job balances. It doesn't say where the dirt goes. For that, keep the balance as you walk the road, the way a bank statement keeps a running total. Each reach's cut is a deposit, each reach's adjusted fill is a withdrawal, and the balance at a station is its mass ordinate. The Handbook's Earthwork formulas define it as "the cumulative total of excavation and embankment at a given station." With excavation counted plus and adjusted embankment minus,

M=∑Vcut−∑VfillSFM = \sum V_{\text{cut}} - \sum \frac{V_{\text{fill}}}{\text{SF}}

with both sums running from the start of the job, where M=0M = 0. Here's a short road worked that way, with a shrinkage factor of 0.90. Each ordinate is the one above it, plus the reach's cut, minus its adjusted fill.

Mass ordinates, with each reach's volumes listed at the station that ends it
StationCut (yd³)Fill (yd³)Fill ÷ 0.90Ordinate (yd³)
0+000
1+000270300−300
2+000450500−800
3+000180200−1,000
4+0040000−600
5+0070000+100
6+0050000+600
7+000360400+200
8+00090100+100
Checkpoint

A mass diagram starts at zero at station 20+00, and the fill has a shrinkage factor of 0.85. What is the mass ordinate at 23+00?

Volumes between stations
ReachCut (yd³)Fill (yd³)
20+00 to 21+006200
21+00 to 22+0041085
22+00 to 23+00150340
23+00 to 24+000595
yd³

Reading a mass diagram

Plot the ordinates against station, and the shape tells the story of the job. The Handbook's Earthwork formulas draw a mass haul diagram under the road's profile, and the figure below follows that layout with the numbers from the table.

profile grade line existing ground fill cut fill mass diagram −1,000 −800 −600 −400 −200 0 +200 +400 +600 mass ordinate (yd³) 0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 station balance line balance line at +100 balance point, 4+86 valley: fill → cut peak: cut → fill ends at +100: waste haul back haul ahead
The road's profile, and its mass diagram below it

Source: Adapted from the FE Reference Handbook, Earthwork formulas

Read the slope first. Where the curve climbs, cut outweighs fill, so the balance grows. Where it falls, fill outweighs cut. So a peak is where cut gives way to fill, here at 6+00, and a valley is where fill gives way to cut, at 3+00. Those are the stations where the ground crosses grade in the profile.

Now lay any horizontal line across the curve. Between two places it meets the curve, the ordinate ends where it started, so the cut in between exactly feeds the fill in between. That's a balance line, and the places it meets the curve are balance points. The zero line meets this curve at 0+00 and 4+86, so the cut from 3+00 to 4+86 fills the stretch from 0+00 to 3+00.

Which way does that dirt travel? Below the balance line, the curve falls before it rises, so the fill comes first in stationing and the cut comes after it. The dirt has to be hauled back, toward lower stations. Above a balance line, as in the hump the line at +100 cuts off between 5+00 and 8+00, the cut comes first and the dirt is hauled ahead on station. That's the whole rule: above the line, haul ahead; below it, haul back.

Last, look at where the curve ends. The final ordinate is what's left over from the whole job: plus is an excess to waste, minus is a shortage to make up from borrow. This road ends at +100 yd³. That's the cut between 4+86 and 5+00, which neither balance line claims.

Checkpoint
1 of 2
−400 −200 0 +200 +400 +600 +800 +1,000 mass ordinate (yd³) 30+00 34+00 38+00 station
A mass diagram from 30+00 to 38+00

Which statements about this job are true?

A.
Station 33+00 is where the road passes from fill into cut.
B.
From 30+00 to 33+00, excavation exceeds embankment.
C.
At 34+83, the road passes from cut into fill.
D.
The cut between 30+00 and 34+83 exactly supplies the fill between them.

Recap

  • Earthwork comes in three volumes: bank in the ground, loose once it's dug, and compacted in the fill. Swell and shrinkage percentages are measured against bank volume unless a question says otherwise.
  • The grains' weight never changes, so volume goes inversely with dry unit weight: SF=Vcompacted/Vbank=γD,bank/γD,compacted\text{SF} = V_{\text{compacted}}/V_{\text{bank}} = \gamma_{D,\text{bank}}/\gamma_{D,\text{compacted}}.
  • Slice the way the ground was measured: end areas along a route, contour areas one interval apart for a pond or knoll, a grid of corner cuts for a borrow pit, and a pyramid where a section runs out. A knoll gives bank volume, and a pond gives compacted volume.
  • Compare cut with fill only in the same state. A fill takes Vfill/SFV_{\text{fill}}/\text{SF} bank yards, and the net is an excess to waste or a shortage to borrow.
  • The mass ordinate is cumulative cut minus cumulative adjusted fill. The curve climbs through cut and falls through fill, peaks and valleys are cut-fill transitions, and between two crossings of a balance line the cut feeds the fill, hauled ahead above the line and back below it. A plus final ordinate means waste, and a minus one means borrow.