Quantity Takeoff

An estimate starts by counting: cubic yards, square feet, and pounds.

A slab on grade is 30 ft by 54 ft and 6 in. thick. Multiply the drawing's numbers, 30 × 54 × 6, divide by 27, and you'd order 360 cubic yards: forty 9-yard truckloads for a slab that needs four. The geometry was fine. The 6 was in inches and the rest in feet, and that one slip orders twelve times the concrete. With the thickness as 0.5 ft, the slab is 810 ft³, or 30 yd³. Most of a takeoff is like this: easy geometry, and unit bookkeeping that has to be exactly right.

Measured the way it's bought

A takeoff turns drawings into quantities an estimator can price, and each item is measured the way it's bought or paid for:

  • Concrete by the cubic yard, the volume poured, which is how ready-mix is sold.
  • Formwork by contact area in square feet, the surface the forms touch. The plywood, the bracing, and the labor to set and strip them grow with the face area, not the volume behind it.
  • Reinforcing steel by weight, in pounds or tons, as the fabricator ships it.
  • Excavation and backfill by the cubic yard. Excavation is measured in the ground, in bank cubic yards (BCY), the starting state in Earthwork Volume States and Hauling. As there, label every volume with its state.

The rest is geometry plus unit bookkeeping: work in feet, convert cubic feet to cubic yards once, and add waste last.

Concrete: feet in, cubic yards out

Every concrete shape in a takeoff is an area times a length. The catch is that drawings mix units: plan dimensions come in feet, and slab and wall thicknesses usually in inches. Put every dimension in feet before you multiply, so a 10 in. wall is 10/12=0.83310/12 = 0.833 ft thick.

  • A slab or footing is length × width × thickness, and a wall is length × height × thickness.
  • A group of columns is one column's cross section times its height, times the number of columns. For a round column, the Handbook's Mensuration of Areas and Volumes gives the cylinder's volume as V=πd2h/4V = \pi d^2 h/4.

Then convert, once. A cubic yard is a cube 3 ft on a side, so it holds 3×3×3=273 \times 3 \times 3 = 27 ft³, a number the Handbook doesn't print. Dividing by 9 instead, which turns square feet into square yards, triples the yards.

An order also carries a waste allowance for spills, bulging forms, and uneven subgrade, stated as a percentage. Add it last, by multiplying the net cubic yards by 1+waste1 + \text{waste}. Multiplication doesn't care when a factor like 1.05 goes in, but making waste the final step is how you make sure it goes in exactly once.

A ready-mix truck carries a set volume, so divide and round up: a quarter of a load still needs a truck. Material cost is the ordered volume, waste included, times the price per cubic yard.

Worked Example Concrete for a foundation wall
1 of 3

A cast-in-place wall is 64 ft long, 10 ft high, and 10 in. thick. With a 5% waste allowance, how many cubic yards should be ordered, and how many 9 yd³ trucks will deliver them?

Formwork: only the faces that need holding

Wet concrete is a heavy liquid, and a form is whatever keeps it from flowing where it shouldn't. Forms are paid for by contact area, the square feet of form face touching the concrete, so count only the surfaces that actually get one. For each surface, ask what holds the concrete there:

  • Soil holds a bottom that sits on it, so the underside of a footing or slab on grade isn't formed.
  • Nothing needs to hold an open top, which is struck off and troweled.
  • Every side face needs a form, and so does the bottom of anything cast in the air.
open top on footing Wall open top on soil Footing open top Beam Column (plan) formed: counts as contact area not formed
Which faces of four common shapes are formed

That settles the four shapes the exam asks about:

  • A wall is formed on both faces: 2 × length × height. Its ends take forms too, if the question counts them.
  • A footing is formed only around its edges: perimeter × thickness.
  • A beam is formed on both sides and its bottom, the soffit: (2×depth+width)×(2 \times \text{depth} + \text{width}) \times length.
  • A column is formed all the way around: perimeter × height, or πd\pi d × height for a round one.
Checkpoint
1 of 3

A foundation wall 50 ft long, 8 ft tall, and 12 in. thick sits on a footing 2.5 ft wide and 1 ft thick that runs the same 50 ft. Leaving out the forms at the two ends, what is the total contact area of the wall and footing forms?

ft²

Reinforcing steel: count, measure, weigh

Steel is sold by weight, but the drawings show bars and lengths, so a rebar takeoff counts the bars, adds up their length, and multiplies by the weight per foot.

Up to #8, a bar's number is its diameter in eighths of an inch, as in Designing Reinforced Concrete Beams, so a #5 bar is 5/8 in. across. The Handbook's ASTM Standard Reinforcement Bars table gives each size's weight per foot:

Diameters and weights of standard bars, #3 through #8
Bar sizeDiameter (in.)Weight (lb/ft)
#30.3750.376
#40.5000.668
#50.6251.043
#60.7501.502
#70.8752.044
#81.0002.670

Source: Adapted from the FE Reference Handbook, Design of Reinforced Concrete Components (ACI 318-14), ASTM Standard Reinforcement Bars

A callout such as #5 @ 12 in. o.c. means #5 bars spaced 12 in. on center. Counting them is a fence-post problem: across 10 ft at 1 ft spacing there are 10 spaces, with a bar at both ends of every one, so there are 11 bars:

number of bars=distance acrossspacing+1\text{number of bars} = \frac{\text{distance across}}{\text{spacing}} + 1

"Each way" means two layers at right angles, and each gets its own count. The bars that run the long way are spaced across the short side, and the bars that run the short way are spaced along the long side.

W = 4s s L = 6s s 5 bars,each L long 7 bars, each W long
A slab mat each way, with bars spaced s on center

A bar usually runs the full dimension, less any end cover the question gives. Where a run is longer than a stock bar, two bars overlap at a lap splice. The lap makes that run longer, but it's still one line in the spacing count, so laps add length, not bars. Multiply the total length by the weight per foot, and add any waste last.

Worked Example Steel for a slab on grade
1 of 2

A 30 ft by 40 ft slab is reinforced with #5 bars at 12 in. on center each way. The bars run the full length of the slab in each direction. Find the weight of steel.

Excavation and backfill

A hole is always bigger than the footing it holds, for two reasons. Workers need room at the bottom to set and strip forms, so the question gives a working space beyond each face, and the bottom width bb is the footing width plus twice that. And unless the sides are shored, they're cut back at a side slope written horizontal to vertical, as in Construction Site Safety. Call the horizontal number nn, so a 1:1 slope has n=1n = 1 and a 3/4:1 slope has n=0.75n = 0.75. Over a depth HH, each wall leans back nHnH, and both walls lean, so the top width is

W=b+2nHW = b + 2nH
n 1 H nH nH w B w b = B + 2w grade backfill footing pier
A sloped pit for a spread footing and pier, in section

A trench keeps the same cross section along its whole length, a trapezoid, so its volume is the average of its top and bottom widths, times the depth, times the length. A pit under a spread footing slopes on all four sides, so its plan grows from the bottom rectangle to the top one. That solid is a prismoid, and the Handbook's Earthwork formulas give its volume by the Prismoidal Formula:

V=L (A1+4Am+A2)6V = \frac{L\,(A_1 + 4A_m + A_2)}{6}

Here A1A_1 and A2A_2 are the bottom and top areas, and LL, the distance between them, is the depth HH. AmA_m is the area at mid-depth, whose sides average the top and bottom sides. It isn't the average of the two areas, and averaging the end areas overstates the pit below by about 7%.

Once the footing is in, the hole is filled back. The backfill is whatever the structure doesn't take up: the excavation less the structure's volume below grade. It ends up as rolled soil, so it's a compacted volume. Finding the bank yards to dig for it is a volume-state conversion, not part of the takeoff.

Worked Example Excavation and backfill for a spread footing
1 of 3

An 8 ft by 8 ft footing, 2 ft thick, carries a 2 ft by 2 ft pier that rises to grade. The pit bottom is 6 ft below grade, with 2 ft of working space around the footing and side slopes of 1:1. Find the excavation and the backfill.

One check before the drawings, on what each line of an estimate reports.

Checkpoint

Which of these pair a work item with the unit it's normally measured in?

A.
Concrete for a spread footing: cubic yards
B.
Reinforcing steel for a slab: linear feet of bar
C.
Formwork for a wall: square feet of contact area
D.
Excavation for a basement: loose cubic yards
E.
Formwork for a column: cubic yards of concrete it holds

Reading the drawings

Every number above came off a drawing, and the exam tests the reading as well as the arithmetic.

Dimensions and notes

A dimension is a number written along a dimension line, which ends in arrowheads or ticks at two extension lines drawn off the edges it measures. U.S. drawings write feet and inches with a dash, so 12'-6" is 12 ft 6 in. Metric drawings give millimeters with no unit written, so 2440 is 2,440 mm. Some agencies print both, with the metric value in brackets: 8'-0" [2440].

Notes say what a number means. MIN. and MAX. make a dimension a limit rather than a size, and TYP. (typical) means it applies wherever the condition repeats. A detail often crowds similar numbers together, so find the one that belongs to what the question names: follow a dimension line to the edges it measures, or find the note that names the thing.

W 3'-0" [915] TYP. 5'-0" [1525] 2'-0" [610] DRIVEWAY PROPERTY LINE SIDEWALK CURB AND GUTTER STREET NOTES: 1. SINGLE DRIVEWAY: W = 10'-0" [3050] MIN., 14'-0" [4265] MAX. 2. DOUBLE DRIVEWAY: W = 18'-0" [5485] MIN., 24'-0" [7315] MAX. 3. DIMENSIONS IN FEET AND INCHES [MILLIMETERS]. RESIDENTIAL DRIVEWAY APPROACH NOT TO SCALE
A city's standard detail for a residential driveway approach
Checkpoint

According to the detail above, what is the minimum width of a single driveway, in millimeters?

A.
4265 mm
B.
4880 mm
C.
3050 mm
D.
5485 mm

Scales

When a length isn't dimensioned, you can measure it at the drawing's scale. Architectural scales give inches of paper per foot, such as 1/4 in. = 1 ft-0 in., for buildings and details. Engineering scales give feet per inch, such as 1 in. = 20 ft, for site plans, roads, and utilities.

Either way, find what one inch of paper stands for: 4 ft at 1/4 in. = 1 ft-0 in., and 20 ft at 1 in. = 20 ft. Multiply a measured length by it to get the actual length, and divide an actual length by it to get the length on paper. As a pure ratio, both need the 12 in. per ft: 1 in. = 20 ft is 1 in. to 240 in., or 1:240, not 1:20.

Common drawing scales
ScaleFamily1 in. on paperRatio
1/8 in. = 1 ft-0 in.Architectural8 ft1:96
1/4 in. = 1 ft-0 in.Architectural4 ft1:48
1 in. = 20 ftEngineering20 ft1:240
1 in. = 50 ftEngineering50 ft1:600
Checkpoint
1 of 2

On a floor plan drawn at 3/8 in. = 1 ft-0 in., a room measures 4-1/2 in. long. How long is the room?

ft

Written dimensions govern

When a written dimension and a scaled one disagree, the written one governs. Scaling is only a check: paper stretches, lines have thickness, and a dimension can be revised without the line being redrawn. And a scale holds only on a full-size print. A reduced or reproduced copy, such as a half-size set or a PDF printed to fit the page, has shrunk, but its scale note hasn't, so it can't be scaled directly.

Checkpoint

A footing detail is marked SCALE: 3/4" = 1'-0" and gives the footing's width as 4'-6". On the print in the site trailer, the footing measures 1-11/16 in. wide. Which of these are correct?

A.
Use 4'-6" for the footing's width in the takeoff.
B.
Use the width the print scales to, since it's the copy on site.
C.
The print is most likely a half-size copy.
D.
Undimensioned lengths on this print can be scaled at 3/4" = 1'-0".

Recap

  • Measure each item the way it's bought: concrete in cubic yards, formwork in square feet of contact area, steel by weight, and excavation in bank cubic yards. Work in feet, divide by 27 once, multiply by 1+waste1 + \text{waste} last, and round truckloads up.
  • Form only the faces something must hold: both faces of a wall, a footing's edges, a beam's sides and soffit, and all around a column.
  • Bars across a distance number distance/spacing+1\text{distance}/\text{spacing} + 1, each way means two counts, and laps add length, not bars.
  • A pit's bottom is the footing plus working space each side, and its top adds 2nH2nH. Backfill is the excavation less the structure below grade.
  • Actual length is the measured length times what one paper inch stands for, so 1 in. = 20 ft is 1:240. Written dimensions govern, and a reduced print can't be scaled.