Flow in Sewers
A sewer carries the most a little below full.
Before this Lesson
- Manning's Equation
- Stations and Grades · Surveying
Lift a manhole cover on a dry afternoon, and you'll see a few inches of wastewater trickling along the floor of a pipe two feet across. Come back in a storm, and the same pipe runs nearly to the top. Either way, the water slides downhill with air above it, so a sewer isn't a pressure main. It's an open channel that happens to be round, and its designer asks channel questions: how much it carries, how deep and how fast a given flow runs, whether the trickle keeps the pipe clean, and how far the pipe drops to the next manhole.
A round open channel
A sewer runs on gravity. Its slope supplies the pull, its wetted wall supplies the drag, and when the two balance, the flow is uniform. That is the balance from Manning's Equation, and the Handbook's version of it, under Hydrology/Water Resources, applies unchanged:
with for feet and seconds and . Here is the slope of the pipe, which in uniform flow is also the slope of the water surface. The only new work is the geometry of a circle.
Flowing full, the water touches the whole circumference, so and . The Handbook doesn't print the result, but it's one line:
That's a quarter of the diameter, not the radius , one more reminder that the hydraulic radius isn't the radius of anything. Pipe sizes come in inches, and wants feet, so an 18-in. pipe has ft and ft.
Now let the pipe drain to exactly half full. The water fills the lower half of the circle, so it has half the area. It touches the lower half of the wall, so it has half the wetted perimeter. The free surface across the middle drags on nothing, as always. Half over half leaves , the same as full.
Same , same slope, same , so the water in a half-full pipe moves exactly as fast as in the full one. With half the area, it carries half the flow. The Handbook writes full-pipe values with a subscript , so half full, and .
Why the last few inches cost flow
Between half full and full, something odd happens. Fill a pipe from the middle toward the top, and both the area and the wetted perimeter keep growing, but not at the same pace. Near the middle, the walls stand nearly upright, so each extra inch of depth adds a strip of water the full width of the pipe and only an inch of wall on each side. Near the crown, the pipe narrows and its wall curves over toward flat. An extra inch there adds only a narrow strip of water, but the water has to climb a long, gently sloping stretch of wall on each side to rise that inch.
The numbers are lopsided. At 95 percent of full depth, the water already has 98 percent of the full area but only 86 percent of the full wetted perimeter. Closing that last 5 percent of depth adds 2 percent more water and 14 percent more wall to drag on it. falls, the water slows, and the flow drops. So a pipe running full carries less than the same pipe running a little below full. Design still treats as the capacity, since the extra is small, and a pipe that close to its crown can seal and run full with the next surge.
Work out and at every depth, divide each by its full-pipe value, run them through Manning's equation, and you have the Handbook's Hydraulic-Element (Partial Flow) Graph for Circular Sewers, under Hydrology/Water Resources. Each ratio compares a pipe with itself, so , , and cancel, and one chart serves every circular pipe.
Adapted from the FE Reference Handbook, Hydraulic-Element (Partial Flow) Graph for Circular Sewers, constant-n curves
The Handbook's graph draws the discharge and velocity curves twice: dashed for constant , which matches Manning's equation and is what this Lesson uses, and solid for an that grows as the pipe empties. Read the solid ones only when a problem says varies with depth.
From a design flow to a depth and a velocity
A problem rarely hands you the depth. It hands you a design flow, such as the sewage a neighborhood sends at its peak hour or, for a storm sewer, the peak runoff from The Rational Method. Then it asks how deep and how fast that flow runs. The chart answers in three moves:
- Find and for the pipe with Manning's equation.
- Divide the design flow by . Find that ratio on the bottom axis, go straight up to the curve, passing the other curves on the way, and read across on the left axis.
- At that same , go across to the curve and read straight down on the bottom axis. Then multiply: and .
The flow is what you know, so you enter the chart through the discharge curve. Reading as if it were the depth ratio is the usual slip, and the chart shows how far off it is: a pipe carrying a quarter of its full flow runs about a third full.
Sewage flows often come in millions of gallons per day. The Handbook's Units and Conversion Factors table gives 1 ft³/sec (cfs) = 0.646317 MGD, so 1 MGD is ft³/sec.
Fast enough to stay clean
Sewage carries grit, sand, and organic solids, and they settle wherever the water slows down. A sewer that runs too slowly grows a bed of sediment that eats its capacity and turns septic. So sewers are laid steep enough to be self-cleansing: the water moves fast enough to scour its own floor. The Handbook prints no sewer velocity criteria, so a problem states the velocity it wants, and 2 ft/sec flowing full is the common one. Half full is the same velocity, so the criterion holds there too.
For a pipe of a given size and , only the slope sets the velocity, so the criterion becomes a minimum slope. Solve the velocity form of Manning's equation for , with :
Square the whole bracket. It's the step people drop, and without it the answer comes out more than ten times too steep.
A smaller pipe has a smaller , so it needs a steeper slope to reach the same speed. Turn the question around, with the slope fixed by the street, and the same equation gives the smallest pipe that reaches the velocity flowing full:
Inverts from manhole to manhole
A sewer runs straight from one manhole to the next, at one slope per run, so its profile is a chain of straight grades. The elevation that matters is the invert, the inside bottom of the pipe, where the water runs. It isn't the crown (the inside top), the outside of the pipe, or the manhole's rim up at the street. The Handbook doesn't cover sewer profiles, so this part you carry in your head.
A sewer's slope is normally stated as a positive fall in the direction of flow, so the downstream invert is lower, by the slope times the horizontal length of the run:
The manholes are usually located by station, and is the difference of their stations in feet, not in stations.
A station is a distance along the line, written with a plus two digits left of the decimal point. Delete the plus to get feet: station 3+75 is 375 ft from the origin, and 9+25 is 925 ft. The distance between them is ft. For more, see Stations and Grades.